Projects
What we surveyed, for whom, and how long it took.
| Project | Scope | Client | Duration |
|---|---|---|---|
| Violet Bank Water Reticulation | Mapping of 400 hectares of village | Bushbuckridge Municipality | 8 days |
| Mananga Village | Mapping of 250 hectares of village | Nkomazi Municipality | 3 days |
| Reivilo Township | Mapping of existing fences and services for town planning, 3 hectares | Greater Taung Municipality | 2 days |
| Phigogo and Kwamkelintaba Water Reticulation | Mapping of 600 hectares of village | SML Projects | 16 days |
| Wesselton Water Reticulation | Mapping of 80 hectares of township | SML Projects | 4 days |
| Retiefville Township | Mapping of 16 hectares of village | Nkolele Projects | 2 days |
| SAPPI Paper Mill | Survey of existing services on the industrial site, including conveyor belts, steelwork, wood chipper, overhead power lines, roads and buildings | ELB Consulting Engineers | 21 days |
| Project | Scope | Client | Duration |
|---|---|---|---|
| Boiphelo Extension 1 Township | Survey of 350 new stands; framing and submitting the General Plan, approved 6 weeks after the Conditions of Establishment were issued | Greater Taung Municipality | 1 day |
| Ridgeview, Extensions 1 to 7 Township | Survey of 3 500 new stands, submitted in 8 phases. Eight General Plans approved 6 to 8 weeks after the Conditions of Establishment for each phase | Dipaleseng Municipality | 8 days |
| Project | Scope | Client | Duration |
|---|---|---|---|
| Nelspruit High Court | Primary benchmarks, precise setting out of concrete and steel, monitoring of high rising structures, as built surveys | Trencon Construction | 18 months |
| SAPPI Paper Mill, new Biomass Plant | Primary benchmarks, precise setting out of piling, concrete and steel, construction monitoring, as built surveys | ELB Consulting Engineers | 12 months |
| Ilanga Mall Extensions | Primary benchmarks, precise setting out of concrete and steel, monitoring of high rising structures, as built surveys | Norse Projects | 18 months |
| Jeppes Reef Bulk Water Supply and Reticulation | Water pipelines: primary benchmarks, setting out of concrete and steel, as built surveys | VMT Construction | 12 months |